Part Number: 803V0102© 2012 Pella CorporationINSTALLATION INSTRUCTIONSIMPERVIA® SLIDING PATIO DOOR WITH FINSInstallation Instructions for Typical Wood
APPLYING INSTALLATION FINSA. Cut the fins to length. Using the following formula, cut the fins to length, making sure the end cut is square on both end
APPLYING HEAD DRIP FIN - REQUIRED FOR VERTICAL MULLION APPLICATIONSA. Apply a bead of sealant along the whole width of the mulled composite behind t
This page left blank intentionally.
YOU WILL NEED TO SUPPLY:Ř Cedar or Impervious shims/spacers (12 to 20)Ř 2" galvanized roofing nails (1/4 lb.)Ř Closed cell foam backer rod/seal
Exterior1D'&()D. Fold the water resistive barrier. Fold side flaps into the opening and staple to the inside wall. Fold the
A. Place three 3/8" beads of sealant. The first bead should be approximately 3/4" from the exterior of the rough opening, the second 2-1/2&q
A. Apply side flashing tape. Cut two pieces of flashing tape 4" longer than the frame height of the door. Apply one piece to each side over the na
Caution: Ensure use of low expansion polyurethane window and door installation foams and strictly follow the foam manufacturer’s recommendations for a
"#Note: Application of closed cell foam backer rod and sealant does not apply to stucco.A. Insert closed cell foam backer rod into the space
MULLING INSTRUCTIONHORIZONTAL MULLIONS:Note: If transoms are to be attached (mulled) to the top of the unit, perform this process before attaching fin
VERTICAL MULLIONS:A. Lay the units on a smooth clean surface, exterior side up to perform these steps.&95&*033*#*/5&*033*##% &&95